PMP Exam Flashcards: Formulas, Terms and the PMI Mindset

The PMP is mostly situational judgement, but earned value formulas, key terms and agile vocabulary are pure recall. What to card, what to practice instead, and a study schedule.

Most PMP exam questions are situational: a scenario describes a project problem and asks what the project manager should do next. Flashcards cannot teach that judgement, practice questions can. But underneath the scenarios sits a layer of pure recall that you need instantly: earned value formulas, a few calculation rules, key terms, and the vocabulary of agile and hybrid approaches, which make up a large share of the exam. That layer is around 150 to 250 cards, and getting it automatic frees your attention for the judgement questions.

(This guide is from the Nebulearn blog, and Nebulearn makes a flashcard app. Exam details change, so check PMI's current Exam Content Outline before you plan.)

What the exam tests

PMI publishes an Exam Content Outline that defines the domains and tasks the exam covers, and it is updated periodically. In recent years the exam has had 180 questions, a mix of multiple choice, multiple response, matching, hotspot and fill in the blank, and draws heavily on agile and hybrid approaches as well as predictive (waterfall) project management. Always confirm the domains, weights and format on PMI's site, since an outdated study guide is a common way to waste weeks.

Part of the examWhere flashcards helpWhat to use instead
Situational judgement ("what should the PM do next?")Very littleHundreds of practice questions, and reading the explanations
Earned value and other calculationsFormulas and their interpretationA few practice calculations to confirm the steps
Terms and artifactsDefinitions, what each document or artifact is forSeeing them used in scenarios
Agile and hybrid vocabularyRoles, events, artifacts, metricsScenario questions about agile teams
The "PMI way of thinking"A small set of principle cardsPractice questions, mostly

Earned value: the cards everyone needs

Earned value management (EVM) questions are among the most predictable on the exam. The formulas are short and exact, which makes them ideal cards. Learn what each one means, not just the formula, because many questions ask you to interpret the result.

FormulaMeaningInterpretation
CV = EV - ACCost varianceNegative means over budget
SV = EV - PVSchedule varianceNegative means behind schedule
CPI = EV / ACCost performance indexBelow 1 means over budget
SPI = EV / PVSchedule performance indexBelow 1 means behind schedule
EAC = BAC / CPIEstimate at completion (if current cost performance continues)Forecast total cost
EAC = AC + (BAC - EV)EAC if remaining work goes at the original rateUsed when the variance was a one-off
ETC = EAC - ACEstimate to completeHow much more will be spent
VAC = BAC - EACVariance at completionNegative means the project will finish over budget
TCPI = (BAC - EV) / (BAC - AC)To complete performance indexEfficiency needed on remaining work to finish on budget

Where: EV is earned value, PV is planned value, AC is actual cost, BAC is budget at completion.

Card each one in three directions: formula from name, meaning from formula, and interpretation from a result. Math formula flashcards covers how to encode formulas so they are usable, not just recitable.

Front: CPI is 0.8. What does that mean?

Back: The project is getting 80 cents of value for every dollar spent. It is over budget.

Front: Which EAC formula do you use if the cost overrun was a one-time event?

Back: EAC = AC + (BAC - EV). Remaining work is expected to go at the planned rate.

A memory aid many candidates use for the four core measures (CV, SV, CPI, SPI): variances are EV minus something, indexes are EV divided by something, and the result is good if it is positive (variances) or above 1 (indexes). Two exceptions deserve their own cards: VAC starts from BAC, and TCPI reads the other way round, where above 1 means the remaining work must be done more efficiently than planned.

Other calculations worth a card

ItemFormula or rule
PERT (beta) estimate(Optimistic + 4 x Most likely + Pessimistic) / 6
Triangular estimate(Optimistic + Most likely + Pessimistic) / 3
Standard deviation (PERT)(Pessimistic - Optimistic) / 6
Communication channelsn(n - 1) / 2, where n is the number of people
Float (slack)Late start - early start, or late finish - early finish
Expected monetary valueProbability x impact, summed across outcomes

Communication channels is a classic: a team grows from 5 to 8 people, how many channels were added? 10 to 28, so 18. Make one card with a worked example like that.

Agile and hybrid vocabulary

A large share of the exam involves agile and hybrid settings, so this vocabulary needs to be automatic.

CategoryTerms to card
RolesProduct owner, scrum master, developers (called the development team in older material), servant leader
EventsSprint planning, daily standup, sprint review, retrospective, backlog refinement
ArtifactsProduct backlog, sprint backlog, increment, definition of done, definition of ready
MetricsVelocity, burndown chart, burnup chart, cycle time, lead time, cumulative flow
PracticesUser stories, story points, MVP, timeboxing, Kanban WIP limits, spikes

Card each term with its purpose (one term per card, per the atomic encoding rule), and add a comparison card for every pair that is easy to confuse: sprint review vs retrospective, burndown vs burnup, definition of done vs acceptance criteria, product owner vs project manager.

Front: Sprint review vs sprint retrospective: what is each for?

Back: Review: inspect the product increment with stakeholders and adapt the backlog. Retrospective: the team inspects its own process and plans improvements.

The PMI mindset, carefully

Much of the exam rewards a particular way of thinking: servant leadership, collaboration, addressing problems early, following the process, and analyzing before acting. Some of this can be captured as short principle cards ("before escalating, the PM tries to resolve it at the team level"), but keep them few. The mindset is learned mostly by doing practice questions and reading why each wrong answer is wrong. A deck of 100 "mindset" cards tends to become rules you recite without being able to apply, the same trap described in flashcards vs practice problems.

Study schedule

Most candidates prepare over 8 to 12 weeks after completing the required 35 hours of project management education.

WeeksFlashcardsPractice
1 to 4Add cards as you study each topic: EVM, calculations, terms, agile vocabulary. 10 to 15 min a day.Topic quizzes
5 to 8Reviews, plus lesson cards from every practice setMixed practice questions, 50 to 100 a week
9 to 12Reviews only, focused on missed cardsFull length timed mock exams, reviewed carefully
Final weekShort daily reviews, EVM formulas once a dayOne last mock early in the week, then rest

The high stakes exam schedule has a general version of this plan, and spaced repetition for working professionals covers fitting reviews around a full time job, which describes most PMP candidates.

Where other resources are better

PMI's own materials, including the Exam Content Outline and its official study resources, define what is tested. Practice question banks and full mock exams from reputable providers are the most important prep tool, since the exam is mostly scenarios. Many candidates also use a prep course, which often includes the 35 contact hours required to apply.

Premade PMP decks exist and can be a quick start for terms and formulas. Check that they match the current outline, and add your own lesson cards from practice exams, since those are personal and the most valuable. Premade decks vs making your own covers the trade off.

In Nebulearn, FSRS schedules the cards so formulas you know stop taking time and the lesson cards you keep missing stay in front of you.

Recall underneath, judgement on top

The PMP tests judgement, but judgement goes faster when the recall layer is automatic. Card the earned value formulas with their meaning and interpretation, the handful of other calculations, the key terms, and the agile vocabulary with comparison cards for confusing pairs. Keep mindset cards few, and let practice questions and your own lesson cards teach the situational thinking.